Eurowind awaits last permits for 66MW wind farm in Romania

acum 9 luni 37

Romania’s energy market regulator ANRE scheduled for endorsement on January 17 the authorization for the establishment of the Frumușita, a 66MW wind farm developed by the Danish group Eurowind, Economica.net reported.

The project company, Frumusita SRL, has already signed a connection contract to the network operated by Distribuție Energie Electrică Romania (DEER).

After ANRE issues the establishment authorization, the project developer must prove that it has the financing for the construction of the energy capacity, so, most likely, this project will be one of those that will be completed and produce electricity.

Eurowind is a Danish renewable project developer with activities in several markets. According to the latest data on its website, the company has a massive portfolio of projects in Romania of 4,000 MW, of which 108 MW are under construction.

Eurowind has been present in the Romanian market since 2011.

(Photo: Welcomia/ Dreamstime)

[email protected]

Sursa: https://www.romania-insider.com/eurowind-permits-wind-farm-ro-jan-2024

Citiți întregul articol

Declinarea răspunderii !!!

SP1.RO este un agregator automat de știri din România. În fiecare articol, preluat de SP1.RO cu maxim 500 de caractere din articolul original, este specificat numele sursei și hyperlink-ul către sursă.

Preluarea informațiilor urmăreste promovarea și facilitarea accesului la informație, cu respectarea drepturilor de proprietate intelectuală, conform cu termenii și condițiile sursei (caleaeuropeana.ro).

Dacă sunteți proprietarul conținutului și nu doriți să vă publicăm materialele, vă rugăm să ne contactați prin e-mail la [email protected] și conținutul va fi șters în cel mai scurt timp posibil.