The harsh winter did not stop the works on the A1

acum 1 ora 2

The National Road Infrastructure Management Company announces that on the A1 Margina – Holdea construction site, the activity is focused on the construction of the tunnels.

„At Tunnel 1 (415 meters in one direction and 367.5 meters in the other), work is being carried out in parallel on both galleries in several stages: applying waterproofing, installing reinforcement, formwork and concreting the final lining. In total, six teams of workers are involved in the two galleries, working in stages, uninterruptedly, depending on the status of each area”, CNAIR reported on Facebook.

In parallel, work is being carried out on Tunnel 2.

„In Tunnel 2 (1,985 meters in one direction and 1,825 meters in the other), ten excavation fronts are open, including the execution of the primary lining, so that the advance can be made simultaneously from several points. In the Margina area, concreting works have begun on the platform for the manufacture of beams, necessary for the next ...

Sursa: https://www.mediafax.ro/english/the-harsh-winter-did-not-stop-the-works-on-the-a1-23693451

Citiți întregul articol

Declinarea răspunderii !!!

SP1.RO este un agregator automat de știri din România. În fiecare articol, preluat de SP1.RO cu maxim 1000 de caractere din articolul original, este specificat numele sursei și hyperlink-ul către sursă.

Preluarea informațiilor urmăreste promovarea și facilitarea accesului la informație, cu respectarea drepturilor de proprietate intelectuală, conform cu termenii și condițiile sursei (caleaeuropeana.ro).

Dacă sunteți proprietarul conținutului și nu doriți să vă publicăm materialele, vă rugăm să ne contactați prin e-mail la [email protected] și conținutul va fi șters în cel mai scurt timp posibil.